Agreement No. CE 7/2008 (EP)

Organic Waste Treatment Facilities,

Phase I Feasibility Study

 

 

Environmental Impact Assessment Report

 

 

Contents

 

1......... INTRODUCTION

Project Background

Objectives of the EIA Study

Consideration of Environmental Impact Assessment Ordinance

EIA Study Area

Structure of the EIA Report

2......... PROJECT DESCRIPTION

Purpose and Objective of the Project

Need for the Project

Consideration of Different Site Options

Outline of Project Elements

Consideration of Alternative Construction Methods and Sequences of Works

Construction Programme

Interactions with Other Projects

3......... AIR QUALITY

Introduction

Environmental Legislation, Standards and Guidelines

Description of the Environment

Air Sensitive Receivers

Potential Source of Impacts

Assessment Methodology

Prediction and Evaluation of Impacts

Recommended Air Quality Mitigation Measures

Evaluation of Residual Impacts

Environmental Monitoring and Audit

Conclusion

4......... HAZARD TO LIFE

Introduction

Study Approach

Study Basis

Hazard Identification

Frequency Estimation

Consequence Analysis

Risk Summation

Risk Mitigation Measure Identification and Analysis

Analysis of Mitigation Measures

Recommended Mitigation and Safety Measures during Construction Phase

Recommended Safety Measures for Plant Design and Operation

Mitigated Scenarios

Conclusion

References

5......... WATER QUALITY

Introduction

Environmental Legislation, Policies, Plans, Standards and Criteria

Description of the Environment

Water Sensitive Receivers

Assessment Methodology

Identification of Environmental Impacts

Cumulative Water Quality Impact

Prediction and Evaluation of Environmental Impacts

Mitigation Measures of Adverse Environmental Impacts

Evaluation of Residual Impacts

Environmental Monitoring and Audit

Conclusion

6......... WASTE MANAGEMENT

Introduction

Environmental Legislation, Policies, Plans, Standards and Criteria

Environmental Guidelines

Assessment Approach and Methodology

Identification of Environmental Impacts

Evaluation of Environmental Impacts during Construction Phase

Evaluation of Waste Impacts for Operational Phase

Mitigation of Adverse Environmental Impacts during Construction Phase

Mitigation of Adverse Environmental Impacts during Operation Phase

Impacts Caused by Handling, Collection and Disposal of Waste

Contamination Preventive Measures

Approach to Prevent Land Contamination

Evaluation of Residual Impacts

Environmental Monitoring and Audit

Conclusion

7......... LANDSCAPE AND VISUAL

Introduction

Project Description

Environmental Legislation and Standards

Methodology of Assessment of Landscape Impacts

Methodology of Assessment of Visual Impacts

Baseline Study

Reviewing of Planning and Development Control Framework

Landscape Resources (LRs)

Landscape Character Areas (LCAs)

Landscape Sensitivity

Tree Survey Results

Zone of Visual Influence (ZVI)

Visual Sensitive Receivers (VSRs)

Landscape Impact Assessment

Visual Impact Assessment

Conclusion

8......... NOISE

Introduction

Environmental Legislation, Policies, Plans, Standards and Criteria

Description of the Environment

Identification of Environmental Impacts

Evaluation of Environmental Impacts

Mitigation of Adverse Environmental Impacts

Environmental Monitoring and Audit

Conclusion

9......... ENVIRONMENTAL MONITORING AND AUDIT

Introduction

Air Quality

Hazard to Life

Water Quality

Waste Management

Landscape and Visual

Noise

10........ CONCLUSIONS AND SUMMARY OF ENVIRONMENTAL OUTCOMES

Summary of EIA Findings

Overall Conclusion

 

11         IMPLEMENTATION SCHEDULE AND RECOMMENDED MITIGATION MEASURES

 

List of Tables

Table 2.1           Summary of Assessment Results for Site Selection

Table 2.2           Strengths and Weaknesses of Anaerobic Digestion and Composting

Table 2.3           Construction Program

Table 2.4           Concurrent Projects

Table 3.1           Hong Kong Air Quality Objectives

Table 3.2           Reference Levels for HCl, HF and VOCs Acute and Chronic Exposure

Table 3.3           Annual Average Concentrations of Air Pollutants in the Latest Five Years (Year 2004 - 2008) at Tung Chung Air Quality Monitoring Station

Table 3.4           Air Sensitive Receivers

Table 3.5           Standards to be Applied for the Emission Level of Cogen Units

Table 3.6           Standards to be Applied to the Emission Level of the Centralized Air Pollution Control Unit

Table 3.7           Emission Level of Centralized Air Pollution Control Unit

Table 3.8           Emission Level of Cogen Units

Table 3.9           Emission Level of Flaring Gas System

Table 3.10         Conversion Factors for Wake-affected Point Sources and Area Sources

Table 4.1           Time Modes for Temporal Variation of Road Population

Table 4.2           Assumed Length and Occupancy of Different Classes of Vehicle

Table 4.3           Projected Traffic Population

Table 4.4           Projected Number of Passengers for Railway Lines

Table 4 5           Population for OWTF during Operation Phase

Table 4.6           Time Modes for Temporal Variation of Population

Table 4.7           Indoor/Outdoor Ratios for Different Population Categories

Table 4.8           Wind Direction Frequencies at Chek Lap Kok Weather Station

Table 4.9           Properties of Chlorine

Table 4.10         Hazardous Scenarios of Chlorine Outflow from the SHWWTW Buildings According to 1992 SHWWTW HA Report

Table 4.11         Hazardous Scenarios of Chlorine Outflow from the SHWWTW Buildings Taking Into Account Use of Reinforced Concrete Panels

Table 4.12         Hazardous Scenarios for Onsite Transport of Chlorine

Table 4.13         Summary of Chlorine Incidents of Water Treatment Plant from MHIDAS

Table 4.14         Properties of Biogas (Natural Gas)

Table 4.15         Hazards Associated with Biogas Storage

Table 4.16         Release Scenarios

Table 4.17         Assessment Criteria for Biogas Hazards

Table 4.18         Hazard Distances

Table 4.19         Summary of Release Frequencies to Outside of Building

Table 4.20         Onsite Road Transport Failure Case Frequencies

Table 4.21         Probability of Fatality

Table 4.22         Summary of PLL

Table 4.23         Feasible Risk Mitigation Measures

Table 4.24         Quantification of Risk Mitigation Measures and Cost Estimation

Table 4.25         Quantification of Risk Mitigation Measures and Cost Estimation

Table 4.26         Estimated ICAF and MJE for Selected Mitigated Measures

Table 5.1           Summary of Water Quality Objectives for the North Western WCZ

Table 5.2           Baseline Marine Water Quality Condition for North Western WCZ

Table 6.1           Estimated Amount of Excavated Materials to be Generated, Reused and Disposed of

Table 6.2           Estimated Amount of C&D Materials to be Generated, Reused and Disposed of

Table 6.3           Summary of Waste Generation during Construction Phase

Table 6.4           Summary of Waste Generation during Operation Phase

Table 6.5           Summary of Waste Handling Procedures and Disposal Routes during Construction Phase

Table 6.6           Summary of Waste Handling Procedures and Disposal Routes during Operation Phase

Table 6.7           Materials used during the Operational Phase of the Project with Land Contamination Potential

Table 7.1           Relationship between Receptor Sensitivity and Impact Magnitude in Defining Impact Significance

Table 7.2           Landscape Resources (LRs) within a 500m Radius of the Site

Table 7.3           Landscape Character Areas (LCAs)

Table 7.4           Landscape Resources (LRs) and Landscape Character Areas (LCAs) and their Sensitivity to Change

Table 7.5           Visual Sensitive Receivers (VSRs) and their Sensitivity to Change

Table 7.6           Visual Sensitive Receivers (VSRs) and their Magnitude of Impacts

Table 7.7           Proposed Landscape and Visual Mitigation Measures for Construction Phase

Table 7.8           Proposed Landscape and Visual Mitigation Measures for Operation Phase

Table 7.9           Significance of Landscape Impacts in Construction and Operation Phases

Table 7.10         Significance of Visual Impacts in Construction and Operation Phases

Table 8.1           Area Sensitivity Ratings (ASRs)

Table 8.2           Acceptable Noise Levels for Construction Work (Restricted Hours)

Table 8.3           Acceptable Noise Levels for Fixed Noise Sources

Table 10.1         Summary of Key Environmental Outcomes / Benefits

Table 11.1         Project Implementation Schedule

 

 

List of Figures

Figure 1.1         Site Location Plan

Figure 2.1         Locations of Potential Sites for Organic Waste Treatment Facilities (OWTF)

Figure 2.2         Preliminary Site Layout

Figure 2.3         Process Flow Diagram (PFD)

Figure 3.1         Site Location Plan and Locations of Representative Air Sensitive  Receivers

Figure 3.2         Contours of Cumulative Maximum 1-hour Average NO2 Concentration in ug/m3 at 8mPD

Figure 3.3         Contours of Cumulative Maximum 24-hour Average NO2 Concentration in ug/m3 at 8mPD

Figure 3.4         Contours of Cumulative Annual Average NO2 Concentration in ug/m3 at 8mPD

Figure 3.5         Contours of Cumulative Maximum 24-hour Average RSP Concentration in ug/m3 at 32.5mPD

Figure 3.6         Contours of Cumulative Annual Average RSP Concentration in ug/m3 at 8mPD

Figure 3.7         Contours of Cumulative Maximum 1-hour Average SO2 Concentration in ug/m3 at 14mPD

Figure 3.8         Contours of Cumulative Maximum 24-hour Average SO2 Concentration in ug/m3 at 14mPD

Figure 3.9         Contours of Cumulative Annual Average SO2 Concentration in ug/m3 at 14mPD

Figure 3.10       Contours of Maximum 1-hour Average HCl Concentration in ug/m3 at 29.5mPD

Figure 3.11       Contours of Annual Average HCl Concentration in ug/m3 at 32.5mPD

Figure 3.12       Contours of Maximum 1-hour Average HF Concentration in ug/m3 at 29.5mPD

Figure 3.13       Contours of Annual Average HF Concentration in ug/m3 at 32.5mPD

Figure 3.14       Contours of Maximum 1-hour Average VOC Concentration in ug/m3 at 32.5 mPD

Figure 3.15       Contours of Odour Concentration in OU /5-sec average (contributed from OWTF emissions only) at 32.5 mPD

Figure 4.1         Consultation Zone

Figure 4.2         Societal Risk Guidelines

Figure 4.3         Population Restrictions Endorsed by the CCPHI

Figure 4.4         Presentation of Consequence Results

Figure 4.5         Hazard Distance due to Biogas Storage

Figure 4.6         WTW Combined Risk - Individual Risk Contours

Figure 4.7         Societal Risk (All Scenarios - Unmitigated)

Figure 4.8         Contribution of OWTF to Societal Risk for Year 2013 Scenario without LLP

Figure 4.9         Societal Risk (Mitigated Scenarios)

Figure 4.10        Location of 3m Height Fence

Figure 7.1         Location Plan

Figure 7.2         Proposed Site Layout Plan and Aerial View

Figure 7.3         Landscape Impact Assessment Area

Figure 7.4         Landscape Character Map of Hong Kong

Figure 7.5         Landscape Resources

Figure 7.6         Landscape Character Areas

Figure 7.7         Visual Sensitive Receivers & Location of View Angles (1 of 3)

Figure 7.8         Visual Sensitive Receivers & Location of View Angles (2 of 3)

Figure 7.9         Visual Sensitive Receivers & Location of View Angles (3 of 3)

Figure 7.10       View Angles from Visual Sensitive Receivers (VSR 1)

Figure 7.11       View Angles from Visual Sensitive Receivers (VSR 2)

Figure 7.12       View Angles from Visual Sensitive Receivers (VSR 3)

Figure 7.13       View Angles from Visual Sensitive Receivers (VSR 4)

Figure 7.14       View Angles from Visual Sensitive Receivers (VSR 5)

Figure 7.15       View Angles from Visual Sensitive Receivers (VSR 6)

Figure 7.16       View Angles from Visual Sensitive Receivers (VSR 7)

Figure 7.17       View Angles from Visual Sensitive Receivers (VSR 8)

Figure 7.18       View Angles from Visual Sensitive Receivers (VSR 9)

Figure 7.19       View Angles from Visual Sensitive Receivers (VSR 10)

Figure 7.20       Landscape Master Plan

Figure 7.21       Aerial View at Opening Year

Figure 7.22       Aerial View – Year 10 of Operation

Figure 7.23       Photomontage View Angle A – Existing Condition

Figure 7.24       Photomontage View Angle A – Unmitigated Impacts

Figure 7.25       Photomontage View Angle A – Day 1 with Mitigation Measures

Figure 7.26       Photomontage View Angle A – Year 10 with Mitigation Measures

Figure 7.27       Photomontage View Angle B – Existing Condition

Figure 7.28       Photomontage View Angle B – Unmitigated Impacts

Figure 7.29       Photomontage View Angle B – Day 1 with Mitigation Measures

Figure 7.30       Photomontage View Angle B – Year 10 with Mitigation Measures

Figure 8.1         Noise Assessment Study Area

Figure 8.2         Nearest Noise Sensitive Receivers to OWTF

 

 


List of Appendices

Appendix 2.1    Summary of Findings of Stage I Exercise

Appendix 3.1     Calculation of Emission Rates of Organic Waste Treatment Facilities

Appendix 3.2    Calculation of the Composite Emission Factors for Each Road Link

Appendix 3.3    Calculation of Emissions from Marine Vessels

Appendix 3.4    Calculation of Emission Rates of Siu Ho Wan Sewage Treatment Works and North Lantau Refuse Transfer Station

Appendix 3.5    Locations of Air Emission Sources in the Assessment 

Appendix 3.6    Predicted Air Quality Assessment Results

Appendix 4.1    Population Data

Appendix 4.2    Historical Incidents Review

Appendix 4.3    Generic Frequency Estimations

Appendix 4.4    Chlorine Dispersion Consequence Results

Appendix 4.5    Sample fN Pairs (Year 2011 Scenario – events relevant to transport of chlorine and OWTF population)

Appendix 4.6    Illustration of Double Membrane Type Gas Buffer